From the first site notice to a final grant, the Irish planning process in plain English, with the timelines that actually matter.
Most people meet the planning system only a handful of times. Knowing the shape of it, and the deadlines, removes most of the stress.
Here is the journey a typical application takes, from preparing to lodge, through the council's decision, to the appeal stage at An Coimisiún Pleanála.
Optional but valuable: a pre-planning discussion with the local authority helps flag issues early. Your drawings, reports and planning case are prepared so the application is complete and robust from day one.
You must tell the public before applying:
The application, drawings, site location map and notices go to the local authority, online through the national planning portal, or by post/email. The clock starts once a valid application is received.
Anyone can make a submission or observation on the application within 5 weeks of it being received, for a €20 fee. Only those who make a submission (and the applicant) can later appeal. We prepare considered submissions where a scheme warrants it.
The authority normally decides within 8 weeks of a valid application. It may first issue a Request for Further Information (RFI), this pauses the clock until you respond, and significant new information can trigger fresh public notices.
The council's decision is not final for 4 weeks. In that window, the applicant or any party who made a submission can appeal to An Coimisiún Pleanála. If no appeal is lodged, the council issues the final grant.
If appealed, the national planning commission reviews the case afresh. It aims to decide within 18 weeks, though complex cases take longer, and it writes to keep parties updated. Its decision replaces the council's.
A permission normally lasts 5 years. Conditions may need to be discharged before you start. In limited circumstances a decision can be challenged by judicial review in the High Court, on a point of law rather than the planning merits.
Strategy, team coordination and a robust application lodged right first time. More →